Articles in Category: New River Garden Apartments

New River Garden Apartments

on Friday, 13 September 2013. Posted in New River Garden Apartments

  • The first 18 units are completely demoed
  • The first 18 units are completely framed
  • The MEP’s are finished roughing in on 14 units, and inspected
  • There are 7 units complete with drywall
  • Next week all 18 units will be roughed in and inspected
  • Sheetrock should finish on the next 18 units
  • We expect 7 units to be painted
  • Cabinets come in on 9/23/2013 and we should have 7 units complete